Field Projects

NitroTech Project Case Studies
Real Jobs. Real Results. Real Documentation.

From Permian Basin gathering system commissioning to Marcellus post-hydrotest drying campaigns, these are examples of the kind of nitrogen work NitroTech executes — and the standard of documentation we deliver on every job.

Project Examples

Nitrogen Projects We Have Executed

Nitrogen DryingPermian BasinPost-Hydrotest16-inch Pipeline

16-Inch Gathering Main Commissioning — Post-Hydrotest Drying

📍 Permian Basin, West Texas

Scope

8.4-mile, 16-inch NPS OD gathering main. Post-hydrotest dewatering and nitrogen drying to -40°F dew point before natural gas introduction.

Challenge

Pipeline had significant elevation change (600 ft drop over the route) with standing water in multiple low points after hydrotest. Tight commissioning window of 18 hours.

Result

Two foam pig passes removed bulk water. Continuous nitrogen drying achieved -40°F outlet dew point in 14 hours. Dew point certificate delivered same day. Gas introduced on schedule.

PurgingPressure TestingMarcellus ShalePennsylvania

Marcellus Shale Gathering Lateral Purge and Pressure Test

📍 Susquehanna County, Pennsylvania

Scope

12 new well laterals (4–6 inch NPS, 0.4–1.2 miles each) requiring nitrogen pressure testing at 1.5× MAOP and purge to below 1% O₂ before gas introduction.

Challenge

Laterals were commissioned in sequence over 3 days to match pad completion schedule. Rapid mobilization between tie-in points across remote northeast PA terrain required.

Result

All 12 laterals pressure tested and purged to specification over 3 days. Pressure tests completed to specification on each lateral. Zero failures, zero re-tests.

InertingCompressor StationUtica ShaleOhio

Compressor Station Pre-Commissioning — Suction and Discharge Circuit Inerting

📍 Utica Shale, Eastern Ohio

Scope

New 4-unit compressor station. Nitrogen purging of all suction manifold, discharge manifold, scrubber vessels, coolers, and interconnect piping before first gas operation.

Challenge

Complex station piping with multiple dead legs, instrument connections, and buried scrubber vessel low points. Operator required O₂ below 0.5% throughout the circuit.

Result

Full station circuit purged to 0.3% O₂ over 9 hours. Instrument connections individually verified. Completion report delivered within 2 hours of job completion.

Nitrogen DryingGulf CoastLouisiana20-inch Transmission

Post-Hydrotest Drying — 20-Inch Gas Transmission Segment

📍 Louisiana Gulf Coast Corridor

Scope

22.5-mile, 20-inch NPS transmission line segment. Post-hydrotest nitrogen drying to -40°F with pigging support for dewatering phase.

Challenge

Large internal volume (~60,000 SCF). Operator required drying to -40°F with continuous dew point logging. Winter ambient temperatures slowed pipe wall moisture release.

Result

Three foam pig passes completed in 4 hours. Nitrogen drying achieved -40°F outlet dew point in 31 hours with continuous monitoring. Full dew point log and certificate delivered.

High-Pressure TestingHaynesville ShaleLouisiana12-inch Pipeline

Haynesville Shale High-Pressure Gathering Line Commissioning

📍 DeSoto Parish, Louisiana

Scope

6.2-mile, 12-inch NPS gathering line operating at 1,200 psig. Nitrogen pressure test at 1,800 psig and purge to below 1% O₂.

Challenge

Required high-pressure nitrogen delivery (1,800 psig test pressure) in a remote north Louisiana location. Standard low-pressure nitrogen equipment insufficient.

Result

High-pressure nitrogen unit deployed. Pressure test completed at 1,800 psig with 8-hour hold. Purges completed to specification. Line commissioned on schedule.

Winter OperationsBakken ShaleNorth DakotaCrude Gathering

Bakken Crude Oil Gathering System — Winter Commissioning Campaign

📍 Williams County, North Dakota

Scope

New crude oil gathering system: 18 segments, 4–8 inch NPS, ranging from 0.5 to 3.2 miles. Commissioned over 6 weeks during winter field conditions.

Challenge

Sustained ambient temperatures of -10°F to -25°F during the commissioning campaign. Equipment required cold-weather operation without performance degradation.

Result

All 18 segments commissioned to specification with no weather-related delays. Cold-weather-rated nitrogen units maintained full performance throughout. All documentation delivered per operator spec.

Refinery TurnaroundIndustrial NitrogenTexasCatalyst Inerting

Refinery Process Unit Turnaround — Nitrogen Purging Campaign

📍 Gulf Coast Refinery (Texas)

Scope

Hydrotreater unit turnaround: nitrogen purging of 12 vessels, 2 fired heaters, 8 heat exchanger circuits, and associated piping. 72-hour turnaround window.

Challenge

Parallel work streams required nitrogen at multiple locations simultaneously. Catalyst bed required continuous nitrogen blanket throughout turnaround.

Result

All vessels purged to below 1% LEL on schedule. Catalyst blanket maintained without interruption. Unit restarted on schedule.

SCOOP PlayOklahomaNitrogen Drying10-inch Pipeline

SCOOP Play Gathering Header Commissioning

📍 Garvin County, Oklahoma

Scope

14-mile, 10-inch NPS gathering header. Post-hydrotest dewatering, nitrogen drying to -40°F, and purge to below 1% O₂.

Challenge

Remote SCOOP play location with limited road infrastructure. Operator had a 24-hour commissioning window tied to well pad completions in the area.

Result

Single high-flow nitrogen unit mobilized. Dewatering and drying completed in 19 hours. Outlet dew point -43°F confirmed. Gas introduction completed within operator's 24-hour window.

Documentation Standard

What You Receive on Every
NitroTech Job

Every project — regardless of size — gets the same field execution and supervision. These records satisfy pipeline operator commissioning requirements, PHMSA inspections, and internal QA audits.

Job Completion Report

Date, location, pipeline description, service performed, specification achieved, personnel, and equipment used.

Purge Log

Timestamped oxygen concentration readings from start to specification, at defined intervals throughout the purge.

Dew Point Log

Complete trend curve showing outlet dew point from start through specification confirmation, with timestamps and final certified reading.

Dew Point Certificate

Signed document confirming outlet dew point achieved specification, with final reading, time, and supervisor signature.

Pressure Test Record

Test pressure, hold duration, temperature readings, pressure stability chart, and pass/fail determination per operator or regulatory specification.

Equipment Calibration Certs

Calibration records for the O₂ analyzer, dew point instrument, and pressure gauges used on your job, with calibration dates and traceability.

We've Worked In Every Major U.S. Basin

From the Williston Basin in the north to the Gulf Coast in the south — NitroTech has nitrogen equipment and field experience in the basins where the work actually happens.

Permian Basin (TX/NM)Marcellus Shale (PA/WV)Utica Shale (OH/PA)Bakken Shale (ND/MT)Haynesville Shale (LA/TX)SCOOP / STACK (OK)Gulf Coast (LA/TX)Eagle Ford (TX)Appalachian Basin (PA/WV/OH)
Request a Quote

Want Results Like These
on Your Next Project?

Tell us your location, pipeline specs, and service type. We'll quote it fast and show up ready to execute.

Request a QuoteView All Services

Related Resources

Part of the HydroTech Family

Need Hydrostatic Testing Too?

NitroTech Rentals is part of the HydroTech Testing family of companies. If your project also requires hydrostatic pressure testing services, our sister company specializes in exactly that — with the same documentation standards and field experience you get from NitroTech.

Visit HydroTech Testing ↗

hydrotechtesting.com

FAQ

Case Studies FAQ

What does a typical NitroTech nitrogen field project look like?+
Most NitroTech projects begin with a planning conversation around scope, pressure, volume, jobsite logistics, and documentation needs. Equipment is staged, the field operation is executed in the agreed sequence (purging, drying, inerting, pigging, etc.), and closeout documentation is provided.
How does NitroTech document field projects?+
Documentation typically includes equipment records, calibration documentation, safety documentation, operator qualifications where applicable, insurance documentation, project-specific planning records, and closeout records matched to operator and regulatory specifications.
Can NitroTech share case studies for similar projects?+
Yes. NitroTech can share case study summaries for similar pipeline, midstream, and industrial nitrogen projects upon request — subject to operator and confidentiality agreements where applicable.